Report for June 2017

Report Date
June 2017

Achievements in Last Period

  • Training for Course Organisers and Preparation of lists for rollout commenced on 5th June
  • Rollout communication issued
  • URL testing completed and ready for rollout
  • URL updated for Reading List service on 12th June
  • Draft Project Closure and Lessons Learned
  • Prep for final Project Board on 27th July
  • Priorisation of developments issued to suppliers

Issues

  • Alma /Leganto workflow issue highlighted a bug in Alma product, request raised to supplier to resolve as soon as possible. Agreement from supplier to fix bug in Aug release. library teams have a workaround in place to cover period from 10th July to 6th Aug. Testing of fix will be available in Sandbox on 23 July.
  • Due to key business resource on annual leave agreement to complete support handover with supplier on 20th July 

Next Steps

  • Alma workflow fix provided 
  • Handover to supplier support
  • Project Board prep and meeting on 27th July
  • Complete Project Closure and Lessons Learned
  • Closure approval

The project status is GREEN

 

20-Jul-2017 Handover to Supplier Support
31-Jul-2017 Closure

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
100.0 days
Activity this month
2.0 days
Activity this year
89.0 days
Activity to date
91.0 days
Estimate to complete current year
8.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Reading List Management System Procurement & Integration
Code
LMP008
Programme
Z. ISG - Library Management Platform (LMP) (closed August 2017)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Jeremy Upton
Current Stage
Close
Status
Closed
Start Date
14-Jul-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
18-Aug-2017
Overall Priority
Normal
Category
Compliance