Report for June 2017
- Report Date
- June 2017
Achievements in Last Period
- Training for Course Organisers and Preparation of lists for rollout commenced on 5th June
- Rollout communication issued
- URL testing completed and ready for rollout
- URL updated for Reading List service on 12th June
- Draft Project Closure and Lessons Learned
- Prep for final Project Board on 27th July
- Priorisation of developments issued to suppliers
Issues
- Alma /Leganto workflow issue highlighted a bug in Alma product, request raised to supplier to resolve as soon as possible. Agreement from supplier to fix bug in Aug release. library teams have a workaround in place to cover period from 10th July to 6th Aug. Testing of fix will be available in Sandbox on 23 July.
- Due to key business resource on annual leave agreement to complete support handover with supplier on 20th July
Next Steps
- Alma workflow fix provided
- Handover to supplier support
- Project Board prep and meeting on 27th July
- Complete Project Closure and Lessons Learned
- Closure approval
The project status is GREEN
| 20-Jul-2017 | Handover to Supplier Support |
| 31-Jul-2017 | Closure |
- Approved budget
- 100.0 days
- Activity this month
- 2.0 days
- Activity this year
- 89.0 days
- Activity to date
- 91.0 days
- Estimate to complete current year
- 8.5 days
- Estimate to complete future years
- 0.0 days