Report for June 2016
- Report Date
- June 2016
Achievements this period
- New project milestones agreed and resources assigned to new dates
- MyEd changes delivered into TEST
- pcounter changes signed off in TEST and delivered into LIVE
- User accepance testing in progress
Issues
None
Next Steps
- Complete user acceptance testing
- Sign off new user documentation for online fine payments
- Sign off business process changes re standard fine for replacement costs
- Sign off business process changes re standard fine for refunds
- Sign off communications plan for changes to print credit and payments of fines
- Complete EqIA
Milestones
11-July-2016 | Acceptance Review |
25-July-2016 | Delivery |
29-Aug-2016 | Closure |
Project Status
The project status is AMBER as the delivery date has been pushed back by two weeks.
- Approved budget
- 106.0 days
- Activity this month
- 6.0 days
- Activity this year
- 70.0 days
- Activity to date
- 70.0 days
- Estimate to complete current year
- 21.0 days
- Estimate to complete future years
- 7.0 days