Report for August 2016

Report Date
August 2016

Achievements this period

  • Deployment sign off review  held
  • Closure review completed by email.
  • Project closed

Issues

  • None

Project Status

The project status is BLUE

Project Status
RAG Status
Time
BLUE
Cost
BLUE
Scope
BLUE
Overall
BLUE
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days