Report for December 19
- Report Date
- December 2019
Achievements in last period
- End of planning approved by WIS 15 Nov 19 but rejected because SM said they hadn’t had time to review. Was resubmitted 6 December to WIS after SM had input and was approved
- Catch up with project sponsor on 2 December
- Revised timescales approved 12 December following industrial action (piccl 3)
- Initial meeting with Service Management and Apps Management to investigate what stats can be extracted from VRS for the audit of cases. Apps Management taken away to do analysis.
Issues
- Due to resourcing within Service Management the timescales for SM tasks is tight on the current plan so SM asked that they be extended – incorporated into revised milestones piccl 3
Next Steps
- Meeting with Angela Laurins 15 January to discuss Library processes
- Risk review being held 16 January
- The follow on workshop was originally scheduled for 15 January but has been rescheduled for 22 January due to BA availability
- Separate meeting to be scheduled with Alex Forrester to run over processes
Commentary: Project is GREEN as new dates have been agreed
Milestones
|
Analysis |
31-Jan-2019 |
|
27-Mar-2020 |
|
|
27-Mar-2020 |
|
|
17-Apr-2020 |
|
|
8-May-2020 |
|
|
22-May-2020 |
|
|
5-Jun-2020 |
|
|
12-Jun -2020 |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 14.0 days
- Activity to date
- 14.0 days
- Estimate to complete current year
- 36.0 days
- Estimate to complete future years
- 0.0 days