Report for October 19
- Report Date
- October 2019
Achievements in last period
- Project kicked off on 11 October 19
- Initial meeting with stakeholders to discuss project brief held 31 October 19
Issues
- Alex Carter wants us to look at an audit of cases in academic areas which was not included in the original estimation so costs may raise now it is in scope
Next Steps
- Provide a version 0.2 of the brief by 8 November 19 and circulate to stakeholders
- Meeting with project sponsor on 7 November 19
- End of planning submitted to WIS
Project is GREEN
Milestones
|
Plan |
15-Nov-2019 |
- Approved budget
- 50.0 days
- Activity this month
- 6.0 days
- Activity this year
- 6.0 days
- Activity to date
- 6.0 days
- Estimate to complete current year
- 44.0 days
- Estimate to complete future years
- 0.0 days