Report for March 2014
- Report Date
- March 2014
Achievements This Period.
- New project manager appointed
- Sign off of most applications using NEWS
- draft re-estimate of remaining project tasks
- new milestones for NEWS migration agreed with business owners and project sponsor
Issues
- NEWS TEST testing has not completed and one problem remains to be estimated.
- The project has no remaining budget
- The project cannot set milestones for deliverables other than the NEWS migration
Next Steps
- Complete testing in NEWS TEST and Achieve ASOR and delivery for NEWS.
- Sign off new estimate for remaining deliverables
- Agree new budget or new scope for project.
| 18-Apr-2014 | ASOR NEWSLIVE | ||
| 21-Apr-2014 | Deploy NEWSLIVE | ||
| 5-May-2014 | Deployment Review NEWS LIVE |
- Approved budget
- 127.0 days
- Activity this month
- 31.0 days
- Activity this year
- 132.0 days
- Activity to date
- 132.0 days
- Estimate to complete current year
- 105.0 days
- Estimate to complete future years
- 0.0 days