Report for June 2014
- Report Date
- June 2014
Achievements This Period.
New milestones agreed.
New deployment date for APPS database migration agreed.
Issues
No issues.
Next Steps
APPS migration to be delivered.
Project to close.
Milestones
| 16-Jul-2014 | 09-Jul-2014 | Deploy APPS LIVE | Deliver |
| 25-Jul-2014 | 23-Jun-2014 | DSOR APPS | Deliver |
| 30-Jul-2014 | 30-Jun-2014 | Closure | Close |
The project RAG status is GREEN
- Approved budget
- 194.0 days
- Activity this month
- 9.0 days
- Activity this year
- 184.0 days
- Activity to date
- 184.0 days
- Estimate to complete current year
- 15.0 days
- Estimate to complete future years
- 0.0 days