Report for June 2014

Report Date
June 2014

Achievements This Period.

 

New milestones agreed.

New deployment date for APPS database migration agreed.

 

Issues

 

No issues.

 

Next Steps

 

APPS migration to be delivered.

Project to close.

 

Milestones

 

 

16-Jul-201409-Jul-2014Deploy APPS LIVEDeliver
25-Jul-201423-Jun-2014DSOR APPS     Deliver
30-Jul-201430-Jun-2014ClosureClose  

 

 

The project RAG status is GREEN

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
194.0 days
Activity this month
9.0 days
Activity this year
184.0 days
Activity to date
184.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Core Technology Updates
Code
ITS103
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Morna Findlay
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
12-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
1
Overall Priority
Higher
Category
Compliance