Report for May 2014

Report Date
May 2014

Achievements This Period.

 

Deployment review for NEWS migration approved.

UAT for APPS migration carried out.

36 business signoffs achieved.

Acceptance Review for APPS migration  held.

 

Issues

 

Lack of communications from business owner with customers re unavailability of BI suite  led to  late cancelation of migration.

Lack of resources in July (when date is suitable for users) means no clarity yet as to when project can be delivered.

 

Next Steps

 

New migration date to be agreed.

APPS migration to be delivered.

 

 

Milestones

 

To be agreed

 

 

 

The project RAG status is REDF pending agreement of new deployment date.

Project Status
Activity
Approved budget
194.0 days
Activity this month
17.0 days
Activity this year
174.0 days
Activity to date
174.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
4.0 days

Project Info

Project
Core Technology Updates
Code
ITS103
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
Morna Findlay
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
12-Aug-2013
Planning Date
n/a
Delivery Date
n/a
Close Date
01-Aug-2014
Programme Priority
1
Overall Priority
Higher
Category
Compliance