Report for May 2014
- Report Date
- May 2014
Achievements This Period.
Deployment review for NEWS migration approved.
UAT for APPS migration carried out.
36 business signoffs achieved.
Acceptance Review for APPS migration held.
Issues
Lack of communications from business owner with customers re unavailability of BI suite led to late cancelation of migration.
Lack of resources in July (when date is suitable for users) means no clarity yet as to when project can be delivered.
Next Steps
New migration date to be agreed.
APPS migration to be delivered.
Milestones
To be agreed
The project RAG status is REDF pending agreement of new deployment date.
- Approved budget
- 194.0 days
- Activity this month
- 17.0 days
- Activity this year
- 174.0 days
- Activity to date
- 174.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 4.0 days