Current project status Report Date RAG Budget Effort Completed Effort to complete July 2014 BLUE 194.0 days 200.0 days 0.0 Content Status Closed Current Stage Close Start Date Monday, 12 August 2013 Close Date Friday, 1 August 2014 Project information Project Code ITS103 Programme ISG - IS Applications Infrastructure (INF) Session 13/14 Organisational Unit IS IT Infrastructure Project Category Compliance Programme Priority 1 Overall Priority Higher