Report for June 2013

Report Date
June 2013

Report by David Watters for June 2013, updated by Morna Findlay 4/6/13

 Achievements in Last Period

  • Migration document for EBIS TEST prepared
  • Migration procedures updated as migration worked through
  • Migration of EBIS TEST completed - tested successfully
  • User testing carried out by E & B staff - problems post-EBIS TEST refresh but these were resolved
  • Acceptance Sign Off passed on 25/06
  • Work on preparations for migration of EBIS LIVE
  • Arrangements made for migration of EBIS LIVE on 15/07

Issues

  • Migration of EBIS TEST delayed because of work taking longer than estimated
  • Archibus client issue caused problems for testing
  •  Delayed testing caused problems for sign-off and plans for next stages
  •  New Archibus virtual client cannot be installed till Septemner - Stefan Kaempf to liaise with USD

Next Steps

  • Preparation for migration of LIVE database
  • Migration of EBIS LIVE planned for 15/07 but now delayed till September
  • Final tasks on new environment planned to be carried out in July nut not delayed till September.

 

Milestones cannot be set until USD commit to  date for upgrading virtual archibus client.

 

 

Project Status
RAG Status
Overall
AMBER
Change Status
Activity
Approved budget
255.0 days
Activity this month
30.0 days
Activity this year
254.0 days
Activity to date
254.0 days
Estimate to complete current year
5.0 days
Estimate to complete future years
13.5 days

Project Info

Project
Implement New Database Tier
Code
ITS100
Programme
ISG - IS Applications Infrastructure (INF)
Project Manager
David Watters
Project Sponsor
David Smyth
Current Stage
Close
Status
Closed
Start Date
16-Aug-2012
Planning Date
n/a
Delivery Date
n/a
Close Date
13-Sep-2013
Category
Compliance

Documentation