MyEd Upgrade - May 2013
- Report Date
- May 2013
Achievements in this period
- TEST environment signed off
- Statistics issues descoped.
- Closure meeting held and closure signed off.
- Completion report signed off.
- Project closure approved.
The project status is BLUE as the project is now closed.
- Approved budget
- 812.0 days
- Activity this month
- 4.0 days
- Activity this year
- 178.0 days
- Activity to date
- 821.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days