MyEd Upgrade and Capacity Re-benchmark - February 2013
- Report Date
- February 2013
Achievements in this period
- Agreement reached between sponsor and IS applications on work remaining for this project to achieve closure
- Agreement reached on estimate of effort for this work and which resources are required.
- Agreement reached that Production management will fund this remaining work.
Outstanding Issues
- New milestones to be agreed
- IS Applications resources to be secured
- Issues with Statistics on LIVE to be resolved
- Outstanding issues on DEV and TEST to be resolved
- Deployment sign off review to be completed.
Next steps
- New milestones to be agreed
- IS Applications resources to be secured
- Issues with Statistics on LIVE to be resolved
- Outstanding issues on DEV and TEST to be resolved
- Deployment sign off review to be completed.
The project status remains at RED as no new milestones have yet been agreed, as the project manager has not yet been able to secure resources.
- Approved budget
- 812.0 days
- Activity this month
- 5.0 days
- Activity this year
- 151.0 days
- Activity to date
- 795.0 days
- Estimate to complete current year
- 18.0 days
- Estimate to complete future years
- 0.0 days