MyEd Upgrade and Capacity re-benchmark - December/January 2013
- Report Date
- January 2013
Achievements in this period
JIRA issues resolved :
- https://www.jira.is.ed.ac.uk/jira/browse/ITS054-187
- https://www.jira.is.ed.ac.uk/jira/browse/ITS054-188
- https://www.jira.is.ed.ac.uk/jira/browse/ITS054-54
The work required for this issue was carried out on 13/12/12 and it is believed that it can be closed.
DEV and TEST environments
In order to ensure that the DEV environment better reflects the TEST and LIVE environments, a second DEV server has been created and work has been carried out to set up both DEV servers to run two tomcats.
An attempt to recreate the LIVE layouts on DEV failed.
Outstanding Issues
- Issues with Statistics on LIVE to be resolved
- Outstanding issues on DEV and TEST to be resolved
- Deployment sign off review to be completed.
Next steps
The project manager has invited the managers of the Development and Development technology teams ( on 8/2/13) in order to agree what work remains to be carried out on DEV and TEST.
The project status remains at RED as the project manager has not yet been able set a closure milestone until agreement is reached on what work must be carried out on DEV and TEST.
Please note - the estimate of 5 days to complete is the Project Manager's estimate and will be updated after the meeting arranged for 8/2/13
- Approved budget
- 0.0 days
- Activity this month
- 10.5 days
- Activity this year
- 145.0 days
- Activity to date
- 795.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days