ITS054 - MyEd Upgrade and Capacity Re-benchmark - September 2012
- Report Date
- September 2012
Achievements in this period
A number of critical JIRA issues resolved and signed off and good progress has been made with the remaining critical JIRAS (11)
Further load testing with real users carried out. It was agreed with the project sponsor and with production management that no more load testing is required.
The project sponsor and programme manager agreed to transfer more days from the programme to the MyEd project.
Outstanding issues
Remaining critical JIRAs with the project team must be signed off. (9)
Erecruitment channel has beed deployed to existing MyEd LIVE but not tested on MyEd TEST
E-expenses channel must be signed off by Finance.
Personal Tutors channel to be signed off
Next steps
Remaining JIRA issues signed off.
Second Acceptance review (9/1012)
Complete TAD, Operational document and other documents for production management
The project status us GREEN on the assumption that the new project estimate will be agreed by WIS.
- Approved budget
- 736.0 days
- Activity this month
- 19.0 days
- Activity this year
- 62.0 days
- Activity to date
- 705.0 days
- Estimate to complete current year
- 44.0 days
- Estimate to complete future years
- 0.0 days