ITS054 - MyEd Upgrade and Capacity Re-benchmark - September 2012

Report Date
September 2012

 

Achievements in this period

 

A number of critical JIRA issues resolved and signed off and good progress has been made with the remaining  critical JIRAS (11) 

Further load testing with real users carried out. It was agreed with the project sponsor and with production management that no more load testing is required.

The project sponsor and programme manager agreed to transfer more days from the programme to the MyEd project.

 

 

Outstanding issues

 

Remaining  critical JIRAs with the project team  must be signed off. (9)

 

Erecruitment channel has beed deployed to  existing MyEd LIVE but not tested on  MyEd TEST

E-expenses channel must be signed off by Finance.

Personal Tutors channel to be signed off 

 

 

Next steps

 

Remaining JIRA issues signed off.

Second Acceptance review (9/1012)

Complete TAD, Operational document and other documents for production management

 

The project status us GREEN on the assumption that the  new project estimate  will be agreed by WIS.

Project Status
RAG Status
Overall
GREEN
Change Status
Activity
Approved budget
736.0 days
Activity this month
19.0 days
Activity this year
62.0 days
Activity to date
705.0 days
Estimate to complete current year
44.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MyEd Upgrade and Capacity Re-benchmark
Code
ITS054
Programme
Z. ISG - Web Integration (WIT) (Closed)
Project Manager
Morna Findlay
Project Sponsor
Simon Marsden
Current Stage
Close
Status
Closed
Start Date
31-Aug-2010
Planning Date
n/a
Delivery Date
n/a
Close Date
31-May-2013
Programme Priority
2
Overall Priority
Normal
Category
Discretionary