Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
- Engagement with senior suppliers - Desktop Services Team and Enterprise Team
- Engagement with Helpline is ongoing
- Technical teams finalised review supplier documentation
- Project schedule drafted
- Engagement with the supplier is ongoing
Issues and Risks
- There is a risk that resources will not be available to the project to deliver the project to schedule
Next Steps
- Project schedule to be finalised and approved
- Project Brief to be finalised
- Stakeholders to be confirmed
- Communication plan to be created
- Complete planning
Future Milestones
future milestones are indicators only until the planning stage is complete
| 31-Jan-2019 | End of Planning |
| 31-Mar-2019 | Delivery |
| 30-Apr-2016 | Closure |
Project Sponsor Commentary / Approval
None at present
| Attachment | Size |
|---|---|
| 31.66 KB |
- Approved budget
- 15.0 days
- Activity this month
- 1.0 day
- Activity this year
- 1.5 days
- Activity to date
- 1.5 days
- Estimate to complete current year
- 13.5 days
- Estimate to complete future years
- 0.0 days