University Calendar - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
May 2019 BLUE 18.5 days 18.0 days 0.1
Content
Status
Closed
Current Stage
Close
Start Date
Monday, 12 November 2018
Planning Date
Thursday, 31 January 2019
Delivery Date
Tuesday, 21 May 2019
Close Date
Tuesday, 28 May 2019
Project information
Project Code
ITI031
Programme
Innovation Programme 2018/19
Session
18/19
Organisational Unit
Information Services Corporate
Project Management Office (if relevant)
ISG PMO
Project Category
Discretionary
Project Classification
Transform
Funding Source
Innovation
Overall Priority
Normal
Student Impact
Project deliverables will be used by staff on behalf of students