Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
Project Brief submitted to ITI Director for approval
|
Objectives for 2017-19 |
Deliverables for 2017-18 |
Comment |
|
O.1 Review of current processes and documentation. Embed and document processes and governance so that PM in ITI is not dependant on an individual, by July 2020 15% of Time |
D.1.1 Publication : Start to Finish lifecycle for a project showing methodology, governance and associated processes D.1.2 Publication : End of Month reporting D.1.3 Publication : Annual Planning Process D.1.4 Better Intra-Divisional Co-operation on ITI projects |
D 1.1 In place, reviewed - to go out to section heads D 1.2 In place, reviewed - to go out to section heads D1.3 Aim is to have a agreed AP timetable in place for 20-21 planning D1.4 Continue with the monthly ITI Managers meeting, reviewing and refining the regular agenda |
|
O.2 Review of Standards, Tools and Techniques The last year as seen the development of ITI’s project brief and deployment checklist. ITI PM’s have also had demos of Jira, Testrail 15% of Time |
D2.1 Standard document for ITI Financial monitoring and reporting for projects D2.2 Governance of Major Project D2.3 Actual Capture |
D2.1 Work with Stephen Rackley to bring in a revised Financial Planning Document for Projects. and to embed the regular financial overview of projects Delivered D2.3 The Major Governance Toolkit will be employed on at least one major project - CIS014 Network Deployment. Delivered D2.4 Pilot and Rollout of JournyX Under review
|
|
O.3 Enhanced Programme and Portfolio Management Current programme and portfolio monitoring and governance is quite light. This should be stepped up. 30% of Time |
D3.1 More time on programme management by MF Work more closely with fixed term PMs and Section Heads on the programme planning and resourcing D3.2 Portfolio Reporting Work with Director on wider, higher engagement with key ITI management processes and activities D3.3 Improved programme and portfolio reporting CIS - minimal programme in 19-20 DST - minimal programme in 19-20 W10 - programme management via programme board RSS - programme management via SG ENT - programme management by Gail Devaney |
D3.1 How can the Programme Level contribute to overall project management D3.2 Working with Director on higher management level activities D3.3 Provide reports to show KPI, progress, delivery D4.4 More active participation in programme boards and steering groups, and more close working with PMs
|
|
O.4 Act as a Local PMO Liaison 5% of Time |
D4.1 Coordination with ISG PMO to ensure ITI keep to good practise as set by PMO and also input into the PMO for ITI, including end of month reporting to SLT |
Continue
|
|
O.5 Line Management and management of Contract PMs 10% of Time
|
D5.1 General Admin : Recruitment, management, training, familiarisation, admin of PM’s - creation of an effective PM team |
Continue Recruitment of two fixed term PMs - one delivered
|
|
O.6 Project Management 25% of Time |
Assumption is MF will run no more than two (major) projects at any one time |
Continue |
|
|
|
Future Milestones
| End of Planning | 30-Aug-2019 |
| Delivery | 24-Jul-2020 |
| Closure | 31-Jul-2020 |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
