Report for December 2018

Report Date
December 2018
Report Date
December 2018

Achievements

  • Interviews complete; successful candidate selected

Issues

  • Candidate cannot start work until April, so project will be delayed until them

Next steps

  • Finalise recruitment/HR paperwork
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Visualising the curriculum
Code
ISI039
Programme
Innovation Programme 2018/19
Management Office
ISG PMO
Project Manager
Scott Renton
Project Sponsor
Gavin McLachlan
Current Stage
Close
Status
Closed
Start Date
15-Oct-2018
Planning Date
31-Oct-2018
Delivery Date
31-Jul-2019
Close Date
31-Jul-2019