Report for June 2019
- Report Date
- June 2019
Achievements this period
- PWC delivered updated document - sponsor has approved content and confirmed project should proceed to closure
- Delivered communications to the sponsor to review and publish
- A new scope addition has been requested by the Sponsor including additional budget for 5 days - PM organised meetings with UoE and PwC
Issues
- N/A
Next steps
- Create a closure report with clear recommendations
- Extend project through July for new scope
Milestones
- A new phase 5 delivery milestone created for July 19 and close moved out to July 26@-
| Stage | Milestone | Due Date | Previous Date | Complete |
|---|---|---|---|---|
| Close | Create closure report | 26-Jul-2019 | No date available | No |
- Approved budget
- 40.0 days
- Activity this month
- 6.0 days
- Activity this year
- 40.0 days
- Activity to date
- 40.0 days
- Estimate to complete current year
- 5.0 days
- Estimate to complete future years
- 0.0 days