Report for April 2019

Report Date
April 2019

Achievements this period

  • PWC delivered updated document and have responded to initial feedback
  • Met with PWC and sponsor to review report and agree next phase - approved
  • Provided an update to ISG WIS

Issues

  • PWC reporting slightly behind original schedule, but the sponsor and key stakeholders have approved
  • Project sponsor has approved a priority piece ahead of this project, we are still assessing any potential impact

Next steps

  • Continue to support PWC and sponsor requirements

Milestones

  • All milestones as of start May:- note deliver milestones are being adjusted and are under review

 

Stage Milestone Due Date Previous Date Complete
Deliver Phase 2: define the strategy, architecture and operating model 12-Apr-2019 No date available Withdrawn
Deliver Phase 3: establish the roadmap 24-May-2019 26-Apr-2019 No
Deliver Phase 4: support establishment of a business plan 31-May-2019 10-May-2019 No
Close Create closure report 07-Jun-2019 No date available No
Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
ISSUE - PwC are tracking behind schedule, having spent longer on establishing a firm basis of understanding the 'as is' UoE IDAM environment. The sponsor has approved the initial deliverable and the delay. A new sponsor led request to prioritise identifying opportunities around two factor authentication may further delay this project, though this is under review.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor Alistair Fenemore has approved as has the PwC lead George Scott.
Activity
Approved budget
40.0 days
Activity this month
7.4 days
Activity this year
25.0 days
Activity to date
25.0 days
Estimate to complete current year
15.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Identity and Access Management (IDAM) Strategy
Code
ISG016
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Adam Wadee
Project Sponsor
Alistair Fenemore
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Jan-2019
Planning Date
09-Feb-2019
Delivery Date
30-Aug-2019
Close Date
20-Dec-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary