Report for March 2019

Report Date
March 2019

Achievements this period

  • PWC delivered 'as is' and it was approved by sponsor and key stakeholders
  • PWC approval confirmed to continue with target state etc

Issues

  • PWC reporting slightly behind original schedule, but the sponsor and key stakeholders are comfortable
  • Slight delay with payment to PWC, finance ticket raised

Next steps

  • Continue to support PWC and sponsor requirements
  • Deliver update to WIS

Milestones

  • All milestones as of end Marcg:-
Stage Milestone Due Date Previous Date Complete  
Analyse Phase 1 - understand the 'as is' environment 26-Mar-2019 08-Mar-2019 Yes

view

Design Phase 2: define the strategy, architecture and operating model 12-Apr-2019 No date available No

view

Build Phase 3: establish the roadmap 26-Apr-2019 No date available No

view

Deliver Phase 4: support establishment of a business plan 10-May-2019 No date available No

view

Close Create closure report 07-Jun-2019 No date available No

view

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
40.0 days
Activity this month
6.5 days
Activity this year
18.0 days
Activity to date
18.0 days
Estimate to complete current year
22.5 days
Estimate to complete future years
0.0 days

Project Info

Project
Identity and Access Management (IDAM) Strategy
Code
ISG016
Programme
ISG Portfolio Projects (OTHISG)
Management Office
ISG PMO
Project Manager
Adam Wadee
Project Sponsor
Alistair Fenemore
Current Stage
Close
Status
Closed
Project Classification
Grow
Start Date
21-Jan-2019
Planning Date
09-Feb-2019
Delivery Date
30-Aug-2019
Close Date
20-Dec-2019
Programme Priority
1
Overall Priority
Normal
Category
Discretionary