Report for November 2019
- Report Date
- November 2019
Achievements this period
- The PwC report on multi factor authentication has now been completed and signed off by the sponsor.
- The project is now in the closure phase.
Issues
- Closure milestone moved out to the end of December to allow the closure review to be completed.
Next steps
- Project closure review and document the outcomes and next steps.
- Close project.
- Approved budget
- 40.0 days
- Activity this month
- 0.5 days
- Activity this year
- 1.0 day
- Activity to date
- 44.0 days
- Estimate to complete current year
- 1.5 days
- Estimate to complete future years
- 0.0 days