Report for September 2019

Report Date
September 2019
Status

Planning, project brief, TAD, and risk assessment completed.

Agreement has been drafted and is with HIE for signing.

Next Steps:
  • Planning to complete remaining deliverables once HIE have signed the agreement:
    • Infrastructure deployment as per solution design
Notes:
  • As planning for remaining activities has not completed, the current project delivery completion date of 28th Feb, and project closure date of 31st Mar are estimates.

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
IoT008 HIE connectivity
Code
IOT008
Programme
WCDI IoT Programme
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Simon Chapple
Current Stage
Execute
Status
Withdrawn
Project Classification
Transform
Start Date
23-Nov-2018
Planning Date
19-Jan-2019
Delivery Date
28-Feb-2020
Close Date
31-Jan-2020
Overall Priority
Normal
Category
Discretionary

Documentation

Not available.