Report for April 2018
- Report Date
- April 2018
Status:
- OrganiCIty node ready for data sharing and initial data copied to the server.
- Two more ACDs deployed to the Meadows.
- However, there is no specific plan for the remaining deployment. These will be deployed as time allows around other work. As a result the estimated completion date for deployment has been pushed out to end of June, but the project remains green , as this is not considered to be a formal issue.
Next Steps
- Continue sharing data via the OrganiCity Node.
- Deployment of remaining audio capture devices
- Agree if the project will be extended to cover the full 12 months of data capture.
Future Milestones
| 30-Jun-2018 |
Deployment of ACDs complete - end of Delivery |
| 20 Jul-2018 | Project Closure. |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days
