Status:

  • OrganiCIty node ready for data sharing and initial data copied to the server.
  • Two more ACDs deployed to the Meadows.
  • However, there is no specific plan for the remaining deployment.  These will be deployed as time allows around other work.     As a result the estimated completion date for deployment  has been pushed out to end of June, but the project remains green , as this is not considered to be a formal issue.

Next Steps

  • Continue sharing data via the OrganiCity Node.
  • Deployment of remaining audio capture devices
  • Agree if the project will be extended to cover the full 12 months of data capture.

Future Milestones

   
30-Jun-2018

Deployment of ACDs complete - end of Delivery

20 Jul-2018 Project Closure.

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Organicity
Code
IoT006
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Ewan Klein
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
08-Jan-2018
Planning Date
07-Feb-2018
Delivery Date
17-Jan-2020
Close Date
31-Jan-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation