Report for February 2018
- Report Date
- February 2018
Achievements in Last Period
- Updated schedule agreed.
- PIA completed and approved.
- Servers built and hardened (some application work still to do on one sever)
- Problem with wireless receiver coverage addressed.
Issues and Risks
- There are several Risks and Issues being managed via the Project RAID log. All are suitably mitigated.
Next Steps
- Testing completed.
- Press release goes out and notices go up in Meadows notice boards.
- Enquiries and complaints process agreed and in place.
- Go-live: ACDs deployed to the Meadows.
- Data shared via the OrganiCity Node.
- Informatics ethics approval.
- Deployment of audio capture devices
Future Milestones
| 12-Mar-2018 | Delivery \ Go-live |
| 06-Apr-2018 |
Deployment of ACDs complete - end of Delivery |
| 20-Apr-2018 | Project Closure. |
- Approved budget
- 0.0 days
- Activity this month
- 0.0 days
- Activity this year
- 0.0 days
- Activity to date
- 0.0 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days