Report Date
January 2018
Achievements in Last Period
Initial Schedule agreed
Proof of concept device built and field tested.
PIA kicked off.
City of Edinburgh Council engaged.
Wireless receiver installed at Main Library.
Speech obfuscation process completed.
Issues and Risks
Risk: There is a risk to UoE and the Edinburgh Region City Deal reputation, if a bad news story regarding monitoring and surveillance in the Meadows were to emerge.
Next Steps
Sign off project brief.
PIA approval
Informatics ethics approval.
Deployment of audio capture devices
Future Milestones
07-Mar-2018
Delivery \ Go-live
21-Mar-2018
Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days
This article was published on Feb 7, 2018