Report for January 2018

Report Date
January 2018

Achievements in Last Period

  • Initial Schedule agreed
  • Proof of concept device built and field tested.
  • PIA kicked off.
  • City of Edinburgh Council engaged.
  • Wireless receiver installed at Main Library.
  • Speech obfuscation process completed.

Issues and Risks

  • Risk: There is a risk to UoE and the Edinburgh Region City Deal reputation, if a bad news story regarding monitoring and surveillance in the Meadows were to emerge. 

Next Steps

  • Sign off project brief.
  • PIA approval
  • Informatics ethics approval.
  • Deployment of audio capture devices

 

Future Milestones

07-Mar-2018  Delivery \ Go-live
21-Mar-2018 Closure
   

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Organicity
Code
IoT006
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Ewan Klein
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
08-Jan-2018
Planning Date
07-Feb-2018
Delivery Date
17-Jan-2020
Close Date
31-Jan-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation