Report for January 2019

Report Date
January 2019

Status

All ACDs have now been deployed to the Meadows.

Data sharing is in place. Access will need to be requested, and comms will go up on the citysounds.eu and\or the iot.ed.ac.uk web sites to announce this.

Next Steps

Continued data collection to end of Nov  2019.

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
RAG Commentary
Description: On-going delays to full ACD deployment and sharing of data, although sufficient amount of ACDs to data capture was completed previously. Impact: Impact is minimal if addressed in the sort term. Plan to resolve: Re-planning has taken place, although the Sponsor was unable to make the meeting. In the absence of the Sponsor at the meeting, but using points provided in an email, we have extended the delivery phase to accommodate deployment of all ACDs and also the start of data sharing (this will not be via an OrganiCity node as initially thought). Although this moves the project out by more than two months, it is our assumption, in the absence of the Sponsor , that the impact of this is sufficiently low to leave the project at Amber status overall.
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Organicity
Code
IoT006
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Ewan Klein
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
08-Jan-2018
Planning Date
07-Feb-2018
Delivery Date
17-Jan-2020
Close Date
31-Jan-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary

Documentation