Report for September 2018

Report Date
September 2018

Status

Due to on-going delays with final ACD deployment and project closure, caused by resource availability and the wider workload, the milestone dates for these activities have been cleared, until re-planning takes place and new firm dates are set.

Next Steps

  • Re-planning to take place in October to identify firm dates for completion of ACD deployment and closure of project.  

Note: The project still remains Green at this time as data is being collected vie the initial ACDs that were deployed. 

 

 

 

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
Within Tolerance
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
0.0 days
Activity this month
0.0 days
Activity this year
0.0 days
Activity to date
0.0 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Organicity
Code
IoT006
Programme
Internet of Things (IOT)
Management Office
ISG PMO
Project Manager
Stephen Taylor
Project Sponsor
Ewan Klein
Current Stage
Execute
Status
In Progress
Project Classification
Transform
Start Date
08-Jan-2018
Planning Date
07-Feb-2018
Delivery Date
17-Jan-2020
Close Date
31-Jan-2020
Programme Priority
1
Overall Priority
Normal
Category
Discretionary