Report for September 2019
- Report Date
- September 2019
Achievements
- Project brief completed and approved
- Introduction to Abacus and new registers
- Work started on updating EOL registers
Issues
- None
Next steps
- Continuation of work on EOL Registers
- Identification of soon-to-be redundant systems & updating of records
| Stage | Milestone | Due Date |
|---|---|---|
| Analyse | Delivery of up to date listings | 29-Nov-2019 |
| Analyse | Updates to Portfolio/Programme Managers | 13-Dec-2019 |
| Analyse | Analysis complete & reports accepted (ASOR) | 17-Jan-2020 |
| Deliver | Delivery point for final migrations | 21-Feb-2020 |
| Deliver | Delivery complete (DSOR) | 28-Feb-2020 |
| Close | Project Closure | 13-Mar-2020 |
- Approved budget
- 50.0 days
- Activity this month
- 4.4 days
- Activity this year
- 4.7 days
- Activity to date
- 4.7 days
- Estimate to complete current year
- 45.4 days
- Estimate to complete future years
- 0.0 days