Annual Infrastructure Rationalisation Decommissioning - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 GREEN 50.0 days 24.7 days 25.3
Content
Status
In Progress
Current Stage
Analyse
Start Date
Monday, 2 September 2019
Planning Date
Friday, 20 September 2019
Delivery Date
Friday, 28 February 2020
Close Date
Friday, 13 March 2020
Project information
Project Code
INF155
Programme
ISG - IS Applications Infrastructure (INF)
Session
19/20
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Funding Source
Core
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students