Current project status Report Date RAG Budget Effort Completed Effort to complete January 2020 GREEN 100.0 days 12.9 days 79.0 Content Status In Progress Current Stage Execute Start Date Tuesday, 15 October 2019 Planning Date Friday, 13 December 2019 Delivery Date Thursday, 19 March 2020 Close Date Thursday, 16 April 2020 Project information Project Code INF153 Programme ISG - IS Applications Infrastructure (INF) Session 19/20 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Compliance Project Classification Run Project Type Implementation Project Size Medium Project Complexity Simple Funding Source Core Overall Priority Normal Student Impact Project deliverables will have no impact on students