Report for October 19
- Report Date
- October 2019
Achievements in last period
- Project brief was approved by team members by 17 Oct
Issues
- Project brief has not been submitted to WIS yet as the showstopping issues with CF2018 in INF135 will also apply to INF152. Project has been suspended until INF135 issues are resolved.
Next Steps
- Project suspended until end of Jan 2020
Commentary
Description: Project is RED. This project is a follow on project of INF135 (INF135 upgrades all ColdFusion version 10 applications, while INF152 upgrades all ColdFusion version 11 applications). Due to the issues encountered as part of INF135, this project has been suspended. Depending on the outcome of INF135, the INF152 will either be re-started later on, or withdrawn.
Impact: This impacts the security of existing applications as CF11 has been out of support since 30 April 2019
Milestones
Suspension end |
31 Jan 20 |
- Approved budget
- 150.0 days
- Activity this month
- 6.0 days
- Activity this year
- 10.0 days
- Activity to date
- 10.0 days
- Estimate to complete current year
- 138.0 days
- Estimate to complete future years
- 0.0 days