Report for December 19

Report Date
December 2019

Achievements in last period

  • Stefan Kaempf confirmed as project sponsor

Issues

  • None this month

Next Steps

  • First draft of brief to be circulated and team brought together to discuss

 

Milestones

Plan

13-Jan-2020

Deliver

31-Mar-2021

Close

15-Apr-2021

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
150.0 days
Activity this month
0.0 days
Activity this year
1.0 day
Activity to date
1.0 day
Estimate to complete current year
98.0 days
Estimate to complete future years
52.0 days

Project Info

Project
Encryption at Rest Rollout (Multiyear 1 of 2)
Code
INF151
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Sue Woodger
Project Sponsor
Bill Lee
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
15-Nov-2019
Planning Date
06-Dec-2019
Delivery Date
31-Mar-2021
Close Date
15-Apr-2021
Overall Priority
Normal
Category
Compliance

Documentation

Not available.