Report for December 19
- Report Date
- December 2019
Achievements in last period
- Stefan Kaempf confirmed as project sponsor
Issues
- None this month
Next Steps
- First draft of brief to be circulated and team brought together to discuss
Milestones
Plan |
13-Jan-2020 |
Deliver |
31-Mar-2021 |
Close |
15-Apr-2021 |
- Approved budget
- 150.0 days
- Activity this month
- 0.0 days
- Activity this year
- 1.0 day
- Activity to date
- 1.0 day
- Estimate to complete current year
- 98.0 days
- Estimate to complete future years
- 52.0 days