Current project status Report Date RAG Budget Effort Completed Effort to complete December 2019 GREEN 150.0 days 1.0 day 150.0 Content Status In Progress Current Stage Plan Start Date Friday, 15 November 2019 Planning Date Friday, 6 December 2019 Delivery Date Wednesday, 31 March 2021 Close Date Thursday, 15 April 2021 Project information Project Code INF151 Programme ISG - IS Applications Infrastructure (INF) Session 19/20 Organisational Unit IS Applications Project Management Office (if relevant) ISG PMO Responsibility Applications Development and Operations Project Category Compliance Project Classification Run Funding Source Core Overall Priority Normal Student Impact Project deliverables will have no impact on students