Report for November 2019

Report Date
November 2019

Achievements

  • Agreed the number of servers required. 
  • 12 servers required in DEV
  • Delay in receiving servers as ITI had a number of requests to fulfill before ours
  • Completed infrastructure design
  • Some TADs have been started
  • Currently progressing with the framework set ups
    • bisso framework has been set up.

    • Static Web has also been set up,

    • next is oauth

Issues

  • No issues

Next Steps

  • Limited progress expected due to Industrial action and booked holidays in December 
  • Continue with any TADs work
    • TADs will be started once the build has been done
  • Progress setting up DEV servers
  • Review Project Estimate (delayed from November)
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
140.0 days
Activity this month
11.0 days
Activity this year
34.0 days
Activity to date
34.0 days
Estimate to complete current year
108.0 days
Estimate to complete future years
0.0 days

Project Info

Project
AppsUtil OS EOL build Centos 7 version
Code
INF150
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Anne Mathison
Project Sponsor
Stefan Kaempf
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
02-Sep-2019
Planning Date
11-Oct-2019
Delivery Date
29-May-2020
Close Date
12-Jun-2020
Overall Priority
Normal
Category
Compliance