Report for November 2019
- Report Date
- November 2019
Achievements
- Agreed the number of servers required.
- 12 servers required in DEV
- Delay in receiving servers as ITI had a number of requests to fulfill before ours
- Completed infrastructure design
- Some TADs have been started
- Currently progressing with the framework set ups
-
bisso framework has been set up.
-
Static Web has also been set up,
-
next is oauth
-
Issues
- No issues
Next Steps
- Limited progress expected due to Industrial action and booked holidays in December
- Continue with any TADs work
- TADs will be started once the build has been done
- Progress setting up DEV servers
- Review Project Estimate (delayed from November)
- Approved budget
- 140.0 days
- Activity this month
- 11.0 days
- Activity this year
- 34.0 days
- Activity to date
- 34.0 days
- Estimate to complete current year
- 108.0 days
- Estimate to complete future years
- 0.0 days