Project Status Reports

Title Report Date Time Cost Scope Overall Change
Report for December 2019 December 2019 GREEN GREEN GREEN GREEN No Change
Report for November 2019 November 2019 RED GREEN GREEN RED No Change

Project Info

Project
Patching Process for Application Components - Implementation
Code
INF148
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Chris Konczak
Project Sponsor
Stefan Kaempf
Current Stage
Initiate
Status
Not Started
Project Classification
Run
Start Date
03-Feb-2020
Planning Date
27-Mar-2020
Delivery Date
27-Nov-2020
Close Date
11-Dec-2020
Overall Priority
Normal
Category
Compliance

Documentation

Not available.