Report for November 2019
- Report Date
- November 2019
Achievements since last report
- Limited project activity due to Project Manager availability
Issues
- Planning milestone reviewed in light of PM availability due to annual leave and other project commitments
- New planning date approved 13/12/2019 , sign off provided by Programme Manager and Project Sposnor
Next Steps
- Draft project brief and review estimations and tasks, ready for approval
- Actions from pre-planning meetings
The project status is GREEN
|
Milestone |
Due Date |
|
Planning complete |
13-Dec-2019 |
|
Delivery complete |
24-Apr-2020 |
|
Closure |
08-May-2020 |
- Approved budget
- 50.0 days
- Activity this month
- 0.5 days
- Activity this year
- 1.1 days
- Activity to date
- 1.1 days
- Estimate to complete current year
- 48.4 days
- Estimate to complete future years
- 0.0 days