Report for October 2019

Report Date
October 2019
Achievements since last report
  • Project initiated
  • Project website created and project manager assigned
  • Pre-planning meetings held with Dev Services and Application Management
  • Project Sponsor confirmed

 

Issues
  • None

 

Next Steps
  • Draft project brief
  • Actions from pre-planning meetings

 

The project status is GREEN

 

Milestone

Due Date

Planning complete

29-Nov-2019

Delivery complete

24-Apr-2020

Closure

08-May-2020

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Has formal escalation taken place?
No
Activity
Approved budget
50.0 days
Activity this month
0.6 days
Activity this year
0.6 days
Activity to date
0.6 days
Estimate to complete current year
49.9 days
Estimate to complete future years
0.0 days

Project Info

Project
Migration of SVN to GIT
Code
INF146
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Kevin Hone
Project Sponsor
Bill Lee
Current Stage
Plan
Status
In Progress
Project Classification
Run
Start Date
01-Nov-2019
Planning Date
13-Dec-2019
Delivery Date
24-Apr-2020
Close Date
08-May-2020
Overall Priority
Normal
Category
Compliance

Documentation

Not available.