Migration of SVN to GIT - full project information

Current project status

Report Date RAG Budget Effort Completed Effort to complete
December 2019 AMBER 50.0 days 2.1 days 49.0
Content
Status
In Progress
Current Stage
Plan
Start Date
Friday, 1 November 2019
Planning Date
Friday, 13 December 2019
Delivery Date
Friday, 24 April 2020
Close Date
Friday, 8 May 2020
Project information
Project Code
INF146
Programme
ISG - IS Applications Infrastructure (INF)
Session
19/20
Organisational Unit
IS Applications
Project Management Office (if relevant)
ISG PMO
Responsibility
Applications Development and Operations
Project Category
Compliance
Project Classification
Run
Project Type
Implementation
Project Size
Small
Project Complexity
Simple
Funding Source
Core
Overall Priority
Normal
Student Impact
Project deliverables will have no impact on students