Report for December 2019
- Report Date
- December 2019
Achievements in Last Period
- CAM, Blogs and MGen all successfully deployed to LIVE
- Deployment Review for CAM, Blogs and MGen achieved
- Limited planning for remainder of work
Issues/Risk
- Planning for remainder of work delayed due to availability (strike and staff illness)
Next Steps
- Complete planning for next stage, i.e. breaking down larger DBs and moving them onto individual VMs
- Secure budget and resources for remaining work
- Replan remaining milestones
Milestones
| CAM BLOGS MGEN migrated to Maria DB on LIVE | 10-Dec-2019 |
| Deployment Review for CAM, BLOGS, MGEN | 19-Dec-2019 |
| Closure | 31-Jan-2020 |
- Approved budget
- 100.0 days
- Activity this month
- 7.0 days
- Activity this year
- 119.0 days
- Activity to date
- 198.0 days
- Estimate to complete current year
- 23.0 days
- Estimate to complete future years
- 0.0 days