Report for December 2019

Report Date
December 2019

Achievements in Last Period

  • CAM, Blogs and MGen all successfully deployed to LIVE
  • Deployment Review for CAM, Blogs and MGen achieved
  • Limited planning for remainder of work

Issues/Risk

  • Planning for remainder of work delayed due to availability (strike and staff illness)

Next Steps

  • Complete planning for next stage, i.e. breaking down larger DBs and moving them onto individual VMs
  • Secure budget and resources for remaining work
  • Replan remaining milestones

Milestones

CAM BLOGS MGEN migrated to Maria DB on LIVE 10-Dec-2019
Deployment Review for CAM, BLOGS, MGEN 19-Dec-2019
Closure 31-Jan-2020

 

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
No
Activity
Approved budget
100.0 days
Activity this month
7.0 days
Activity this year
119.0 days
Activity to date
198.0 days
Estimate to complete current year
23.0 days
Estimate to complete future years
0.0 days

Project Info

Project
MySQL Environment Migration
Code
INF143
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Tim Gray
Project Sponsor
Stefan Kaempf
Current Stage
Execute
Status
In Progress
Project Classification
Run
Start Date
08-Oct-2018
Planning Date
14-Nov-2018
Delivery Date
10-Dec-2019
Close Date
31-Jan-2020
Programme Priority
4
Overall Priority
Highest
Category
Compliance

Documentation