Report for June 2019

Report Date
June 2019

It has been agreed with heads of Production and Development to close the project, with a new project in 19-20 to continue the SVN work. Development Team will need to re-assess their approach and commitment to availability accordingly.

 

Achievements this period

  • resource clarification and assignments - not achieved
  • VSS completed

Issues

  • software development resources still not booked

Next Steps

  • closure of project

 

Milestones

Close Closure 12-Jul-2019      

 

Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Time
No Change
Cost
No Change
Scope
Significant
Overall
Significant
Has formal escalation taken place?
No
Change Commentary
It has been agreed to close the project and continue the SVN migrations within a new project
Activity
Approved budget
50.0 days
Activity this month
5.0 days
Activity this year
24.0 days
Activity to date
24.0 days
Estimate to complete current year
1.0 day
Estimate to complete future years
0.1 days

Project Info

Project
Migration of VSS and SVN to GIT
Code
INF141
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Nigel Binns
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
29-Oct-2018
Planning Date
30-Nov-2018
Delivery Date
28-Jun-2019
Close Date
12-Jul-2019
Programme Priority
1
Overall Priority
Normal
Category
Compliance