Report for May 2019
- Report Date
- May 2019
- Report Date
- March 2019
Achievements this period
- resource clarification and assignments - not achieved
Issues
- software development resources still not booked
Next Steps
- resource clarification and assignments to the development team
Milestones
| Complete Data on VSS Projects | 31-May-2019 |
| Complete Data on SVN Projects | 31-May-2019 |
| Complete Migrations | 28-Jun-2019 |
| Closure | 12-Jul-2019 |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 11.0 days
- Activity to date
- 11.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days