Report for May 2019

Report Date
May 2019
Report Date
March 2019

Achievements this period

  • resource clarification and assignments - not achieved

Issues

  • software development resources still not booked

Next Steps

  • resource clarification and assignments to the development team

 

Milestones

Complete Data on VSS Projects 31-May-2019
Complete Data on SVN Projects 31-May-2019
Complete Migrations 28-Jun-2019
Closure 12-Jul-2019

 

 

Project Status
RAG Status
Time
AMBER
Cost
GREEN
Scope
GREEN
Overall
AMBER
RAG Commentary
Description of issue/risk Software resource has still not been assigned to the project so that the preparatory work from Production can be taken and used to migrate the applications from SVN to GIT. VSS is completed. /// Impact Very unlikely that migration from SVN to GIT will complete by 31 July as Head of Dev Services had wanted. However, no impact on operational activity. /// Plan to resolve issue/manage risk Programme Manager has organised a meeting with Development Lead, Resource manager and Production next week to confirm when and whether resources are going to be made available to the project. Project will plan into 2019-20 using expected
Change Status
Time
No Change
Cost
No Change
Scope
No Change
Overall
No Change
Has formal escalation taken place?
Yes
Escalated to
Project Sponsor and Programme Manager
Activity
Approved budget
50.0 days
Activity this month
2.0 days
Activity this year
11.0 days
Activity to date
11.0 days
Estimate to complete current year
20.0 days
Estimate to complete future years
0.0 days

Project Info

Project
Migration of VSS and SVN to GIT
Code
INF141
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Nigel Binns
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Project Classification
Run
Start Date
29-Oct-2018
Planning Date
30-Nov-2018
Delivery Date
28-Jun-2019
Close Date
12-Jul-2019
Programme Priority
1
Overall Priority
Normal
Category
Compliance