Report for March 2019
- Report Date
- March 2019
- Report Date
- March 2019
Achievements this period
- resourcing - partially achieved
- published migration instructions
Issues
- software development resources booked - still not completely resourced
Next Steps
- resource clarification and assignments
- review approach, plan and process with Bill Lee and tean
Milestones
| Analyse | Complete Data on VSS Projects | 31-May-2019 | 12-Dec-2018 | No | |
| Analyse | Complete Data on SVN Projects | 31-May-2019 | 12-Dec-2018 | No | |
| Deliver | Complete Migrations | 28-Jun-2019 | 29-Mar-2019 | No | |
| Close | Closure | 12-Jul-2019 | 30-Apr-2019 | No |
- Approved budget
- 50.0 days
- Activity this month
- 2.0 days
- Activity this year
- 11.0 days
- Activity to date
- 11.0 days
- Estimate to complete current year
- 20.0 days
- Estimate to complete future years
- 0.0 days