Report for January 2019
- Report Date
- January 2019
- Report Date
- December 2018
Achievements this period
- compile draft list of apps - partially achieved - enough to start work
- meeting to review and prioritise list - achieved
- resources booked - still not resourced
- created Jira stubs, one for each of the 27 applications assigned a provisional migration category
Issues
- software development resources booked - still not resourced
- PM leaving
Next Steps
- resourcing
- delivery dates checked
- new PM
Milestones
| Analyse | Complete Data on VSS Projects | 19-Dec-2018 |
| Analyse | Complete Data on SVN Projects | 19-Dec-2018 |
| Analyse | Migration Decision | 09-Jan-2019 |
| Deliver | Complete Migrations | 29-Mar-2019 |
| Close | Closure | 30-Apr-2019 |
- Approved budget
- 50.0 days
- Activity this month
- 1.0 day
- Activity this year
- 7.7 days
- Activity to date
- 7.7 days
- Estimate to complete current year
- 42.3 days
- Estimate to complete future years
- 0.0 days