Monthly Project Report
- Report Date
- May 2019
Achievements
Python
- Python completed UAT in May
- Python went LIVE on 29-May
Bamboo
- Bamboo deprecated 40 plans
Issues
-
No issues
Next Steps
Python
- Meeting planned in June with technology Management to discuss how Python should be maintained in the future
ASTA
- ASTA versions to be discussed with the supplier in June
- ASTA requirements will be completed in June
- ASTA JIRAs to be set up for the tasks required in June
Bamboo
- Sign off Bamboo UAT
- Agree and schedule Bamboo Go Live
- Set up Service Alert for Bamboo
- Set up Go Cab for Bamboo
- Bamboo deployed to LIVE
Oracle Grid
- Dev Tech will be looking into Oracle Grid in early June
- Dev Tech will be implementing Oracle Grid in June
Sentry
- Sentry UAT is planned for early June
- Sentry is planned for 2nd week in June
PMP
- PMP UAT in June
- PMP Live Planned for July
GREEN RAG status
Milestones
| Stage | Milestone | Date |
| Accept | Oracle Grid Acceptance Signoff | 06-Jun-2019 |
| Accept | Sentry Build / Acceptance Signoff | 07-Jun-2019 |
| Accept | Bamboo Build / Acceptance Signoff | 12-Jun-2019 |
| Deliver | Sentry Deployed Signoff | 12-Jun-2019 |
| Design | ASTA Requirements Design Signoff | 17-June-2019 |
| Deliver | Oracle Grid Deployed Signoff | 20-Jun-2019 |
| Deliver | Bamboo Deployed Signoff | 24-Jun-2019 |
| Accept | Over All Build / Acceptance Sign Off | 28-Jun-2019 |
| Accept | PMP Build / Acceptance Signoff | 28-Jun-2019 |
| Deliver | ASTA Requirements Document Signoff | 28-June-2019 |
| Deliver | PMP Deployed Signoff | 12-Jul-2019 |
| Deliver | Overall Deployment Sign-Off | 12-Jul-2019 |
| Close | Close | 02-Aug-2019 |
- Approved budget
- 152.0 days
- Activity this month
- 7.0 days
- Activity this year
- 83.0 days
- Activity to date
- 83.0 days
- Estimate to complete current year
- 69.0 days
- Estimate to complete future years
- 0.0 days