Report for April 2017

Report Date
April 2017

Achievements in Last Period

  • Completion report drafted & distributed
  • Closed project

Issues and Risks

​Next Steps

Project Status
RAG Status
Overall
BLUE
Change Status
Activity
Approved budget
75.0 days
Activity this month
0.7 days
Activity this year
74.9 days
Activity to date
74.9 days
Estimate to complete current year
0.0 days
Estimate to complete future years
0.0 days

Project Info

Project
16-17 Infrastructure Rationalisation
Code
INF122
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
David Watters
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
09-Aug-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
05-May-2017
Programme Priority
4
Overall Priority
Normal
Category
Compliance

Documentation