December Report

Report Date
December 2016

Achievements in Last Period

  • Confirmation from Project Sponsor that TADs can be uploaded onto SharePoint Site
  • Agreed final activity to be completed on project before closure
  • Project Completion report drafted and issued out for initial review

Issues

  • Draft Disaster Recovery Plan issued out for review and agreement by project team, currently being reviewed by Project Sponsor and Business Lead
  • Project milestones have been reviewed / agreed with the project team with unspent resource effort of 25 days returned to the INF Programme as per agreement with Programme Manager and Project Sponsor, overall budget now set at 75 days.

Next Steps

  • Application Management Teams to comment on SharePoint structure for TAD storage by 16 Jan
  • Update latest TAD versions to SharePoint
  • Draft DR plan review and update, then pass to IS Change Service Based theme
  • Update Deployment Checklist template to include changes to storage of TAD on projects website
  • Agree completion report and close project

The project status is GREEN

31-Jan-2017 Priority Services DR Documentation complete
14-Feb-2017 Delivery Complete
21-Feb-2017 Closure
Project Status
RAG Status
Time
GREEN
Cost
GREEN
Scope
GREEN
Overall
GREEN
Change Status
Activity
Approved budget
75.0 days
Activity this month
1.4 days
Activity this year
14.2 days
Activity to date
31.3 days
Estimate to complete current year
16.6 days
Estimate to complete future years
0.0 days

Project Info

Project
Disaster Recovery for Priority Services
Code
INF120
Programme
ISG - IS Applications Infrastructure (INF)
Management Office
ISG PMO
Project Manager
Karen Stirling
Project Sponsor
Stefan Kaempf
Current Stage
Close
Status
Closed
Start Date
05-Apr-2016
Planning Date
n/a
Delivery Date
n/a
Close Date
03-Mar-2017
Programme Priority
3
Overall Priority
Normal
Category
Discretionary