June Report
- Report Date
- June 2016
Achievements in Last Period
- Commenced Analysis activity to review all applications & components which make up the Top Priority Services (12 in total)
- Template created to capture relevant information and dash board format produced, currently using this as an Excel spreadsheet via One Drive
- Identified that there will be services which are currently on old version of Technical Architecture Document – team agreed the project would not transfer to new format at this stage
- Graeme Wood to be ITI contact for project
Issues
N/A
Next Steps
- Continue analysis review for Medium Priority Services
- Review and agree storage options for a master DR document which can be stored off site
The project status is GREEN
- Approved budget
- 100.0 days
- Activity this month
- 5.3 days
- Activity this year
- 9.0 days
- Activity to date
- 9.0 days
- Estimate to complete current year
- 16.5 days
- Estimate to complete future years
- 74.9 days