May Report
- Report Date
- May 2016
Achievements in Last Period
- Planning activities completed following review of project brief, plan and estimates
- Stakeholder and Risk Logs created
- High level review of disaster recovery plans available for Top and Medium priority services to assist completion of project brief
- Project brief approved at WIS on 03/06/16
- Resource allocated from Dev Tech and Tech Man
- Project team meetings set up for every 2 weeks
Issues
- N/A
Next Steps
- Commence Analysis activity to review all applications & components which make up the Top and Medium priority services (27 in total)
- Review storage options for a master DR document which can be stored off site
The project status is GREEN
- Approved budget
- 100.0 days
- Activity this month
- 3.2 days
- Activity this year
- 3.4 days
- Activity to date
- 3.4 days
- Estimate to complete current year
- 33.5 days
- Estimate to complete future years
- 61.0 days