Report for February 2017
- Report Date
- February 2017
Achievements in Last Period
- Agreed Deployment Checklist template to include changes to storage of TAD on projects website
- Agreed completion report and project closure
- Communication issued out to key contacts in Production Management and Development Services advising OGG agreement to store TADs on SharePoint Site
Issues
- PICCL raised for 33 days unspent resource effort returned to the INF Programme on project closure as per agreement with Programme Manager and Project Sponsor, a PICCL has been raised and submitted for approval on project closure.
Next Steps
- Technical resource to add TAD documentation to SharePoint site
The project status is GREEN
- Approved budget
- 42.0 days
- Activity this month
- 2.1 days
- Activity this year
- 18.3 days
- Activity to date
- 35.4 days
- Estimate to complete current year
- 0.0 days
- Estimate to complete future years
- 0.0 days